Solar DC cable engineering reference
4 mm² VS 6 mm²
4 mm² or 6 mm² H1Z2Z2-K Solar Cable?
DESIGN CURRENT • THERMAL CAPACITY • VOLTAGE DROP • CONNECTOR FIT
DIRECT ANSWER
Choose 4 mm² or 6 mm² H1Z2Z2-K cable only after checking four gates: circuit design current, installed current-carrying capacity, voltage drop and loss over the full DC loop, and compatibility with connectors and equipment terminals. A 6 mm² copper conductor normally has lower resistance, but it is neither automatically required nor automatically sufficient.
The familiar question sounds binary. Real PV design is not. The same module string may be acceptable on 4 mm² in one layout and require 6 mm²-or more-in another because route length, rooftop temperature, grouping, installation method or the voltage-drop criterion has changed.
This guide gives EPC, design and procurement teams a repeatable screening method. Final approval still belongs to the responsible project designer using the governing code, controlled manufacturer data and actual project conditions. If the cable standard, voltage class or installation environment has not yet been fixed, begin with the Solar DC Cable Selection Guide.
01
DESIGN CURRENT
02
THERMAL CAPACITY
03
VOLTAGE DROP
04
COMPATIBILITY
THE SHORTLIST
When Does Each Size Usually Enter the Shortlist?
4 mm²
May remain viable for modest-current string circuits with shorter routes, acceptable corrected ampacity and voltage drop, and compatible terminations.
6 mm²
Commonly enters the shortlist when routes are longer, losses must be reduced, thermal correction narrows the 4 mm² margin or the project standardizes on a larger string cable.
Neither size should be approved from a rule of thumb. If 6 mm² fails the thermal, voltage-drop, terminal or code check, evaluate 10 mm² or redesign the route.
What Changes When Conductor Size Changes?
Nominal cross-sectional area is not a current rating. It identifies conductor size; the complete cable construction and installation conditions determine circuit performance. The values below are current SINELINK product-page examples and are not universal values for every H1Z2Z2-K cable.
|
Property
|
4 mm² example
|
6 mm² example
|
Design implication
|
|
Nominal area
|
4.0 mm²
|
6.0 mm²
|
Larger nominal area generally lowers resistance.
|
|
Max. resistance at 20°C
|
5.09 Ω/km
|
3.39 Ω/km
|
Adjust for calculation temperature as required.
|
|
Overall diameter
|
5.50 mm
|
6.10 mm
|
Check seals, glands, routing and bend radius.
|
|
Same current and route
|
Higher resistive drop/loss
|
Lower resistive drop/loss
|
Quantify whether the difference is material.
|
Review the available size range on the EN 50618 H1Z2Z2-K solar cable page, then confirm the controlled datasheet and certificate scope for the proposed order.
Establish the Circuit Design Current
Begin with the actual circuit. A module string, parallel-string output, combiner-to-inverter circuit and battery-connected DC circuit do not share one design current.
- Identify the circuit boundaries and any parallel strings.
- Record module short-circuit current and relevant gain assumptions.
- Apply required design multipliers and protective-device coordination.
- Use the same documented design current in thermal and voltage-drop checks.
- Recheck the calculation after a module substitution.
Do not size a module-string conductor from inverter power divided by nominal DC voltage. That shortcut can obscure the actual string-current basis and parallel paths.
Check Installed Current-Carrying Capacity
Published current-carrying tables are reference-condition values. Convert them into an installed rating using the project method and applicable correction factors. Review ambient and roof temperature, cable grouping, conduit or tray arrangement, ventilation, thermal insulation, soil or duct conditions, loaded conductors and termination limits.
THERMAL GATE
Pass only when the corrected current-carrying capacity is at least the required design current. Do not copy an ampacity from another cable construction or installation reference and present it as a product guarantee.
For rooftop temperature mechanisms, read Solar Cable for High-Temperature Rooftops.
Calculate Voltage Drop and Cable Loss
For a simple two-conductor DC run, use the full outgoing and returning conductor loop:
Rloop = 2 × L × Rconductor
ΔV = I × Rloop
Voltage drop (%) = (ΔV ÷ Voperating) × 100
Ploss = I² × Rloop
L is the one-way route length in kilometres, I is circuit current in amperes, and conductor resistance is in ohms per kilometre at the calculation temperature. Copper resistance rises with temperature, so a 20°C catalogue value is a comparison input-not the final hot-operating result.
Illustrative screening example
Assume a 100 m one-way route, 15 A circuit current, 1,000 V operating voltage and the example maximum conductor resistance at 20°C. Temperature correction, connections and additional tolerances are excluded.
|
Size
|
Loop resistance
|
Voltage drop
|
Drop at 1,000 V
|
Cable loss
|
|
4 mm²
|
1.018 Ω
|
15.27 V
|
1.527%
|
229.05 W
|
|
6 mm²
|
0.678 Ω
|
10.17 V
|
1.017%
|
152.55 W
|
|
Difference
|
0.340 Ω
|
5.10 V
|
0.510 points
|
76.50 W
|
The comparison shows why route length matters. It does not prove either size compliant. Recalculate at design temperature and verify the thermal and termination gates.
Verify Connector and Equipment Compatibility
Upsizing changes more than resistance. Cable outer diameter, conductor construction and crimp geometry must fit the connector variant, seal, contact and approved tooling. The same review applies to combiner-box terminals, inverter terminals, glands and cable-entry space.
- Confirm conductor-size and cable-OD ranges.
- Use the specified contact and seal variant.
- Confirm conductor class and strand construction.
- Use the specified stripping dimension, tool and die.
- Do not cross-mate brands or families unless explicitly approved.
The MC4-EVO 2 DC 1500V PV connector page is a commercial entry point; the exact approved cable-contact-seal-tool combination remains controlling.
Compare Installed and Life-Cycle Cost
A larger conductor costs more per metre and can require different contacts, seals, tooling or logistics. It can also reduce resistive loss over years of operation. Compare compliant options using cable and connector cost, installation labour, energy value, inventory complexity and rework risk-not reel price alone.
Decision Scenarios
|
Outcome
|
Conditions that may support it
|
Required caution
|
|
4 mm² remains viable
|
Thermal and drop gates pass; route is short; terminations fit.
|
Not approved until all project evidence is checked.
|
|
6 mm² is preferred
|
Lower resistance materially improves loss or thermal margin.
|
Confirm connector, gland and terminal fit.
|
|
Evaluate 10 mm² or redesign
|
6 mm² fails a gate or the route/current is substantially higher.
|
Do not force a binary 4/6 decision.
|
|
Both are viable
|
Both pass every gate.
|
Compare installed cost and standardization.
|
A Calculation-Led EPC Process
- Freeze the circuit, route and applicable rules.
- Calculate design current and protection coordination.
- Obtain controlled cable data.
- Apply installation and temperature corrections.
- Calculate hot-condition loop voltage drop and loss.
- Verify connector, terminal, gland and routing compatibility.
- Compare compliant alternatives commercially.
- Approve the calculation, datasheet, certificate and inspection plan together.
- Recheck whenever a key input changes.
Minimum Data for a Cable Request
- Circuit ID, source and destination equipment.
- Module/string configuration and design-current basis.
- One-way route length and operating voltage.
- Temperature, grouping and installation method.
- Permitted voltage drop and loss criterion.
- Cable designation, conductor data and required standard.
- Cable OD, connector, contact, seal and gland.
- Marking, color, reel length and traceability requirements.
For coordinated cable, connector and accessory supply, connect the approved schedule to the photovoltaic power station cable solution.
Common Sizing Mistakes
01 Choosing 4 mm² because it is common.
02 Choosing 6 mm² because it feels safer.
03 Using free-air ampacity for a grouped hot-roof route.
04 Forgetting the return conductor in voltage drop.
05 Using 20°C resistance as the hot result.
06 Checking thermal capacity but not voltage drop.
07 Assuming every connector accepts both sizes.
08 Failing to recalculate after inputs change.
FAQ
Q: s 6 mm² always better than 4 mm²?
No. It normally offers lower resistance, but costs more and can change connector or routing requirements. Select the smallest compliant option-or another size-using all four gates.
Q: Can 4 mm² be used for a 15 A solar string?
Possibly, but current alone is insufficient. Check corrected current-carrying capacity, route length, voltage drop, temperature, grouping and terminations.
Q: How much voltage drop is acceptable?
Use the criterion in the project specification and governing design framework. There is no universal percentage for every PV project.
Q: Can the same connector be used for both sizes?
Only if the exact contact and seal configuration permits the conductor and cable-diameter ranges. Verify approved documentation and tooling.
Q: When should an EPC consider 10 mm²?
When 6 mm² fails a thermal or voltage-drop gate, or a larger size has a justified system-level benefit. Check equipment terminals and installation feasibility.
Q: Does EN 50618 select the conductor size?
No. It defines requirements for a PV cable product family; project conductor sizing remains a system-design task.
REQUEST A DATA REVIEW
Send the calculation inputs-not only "4 mm² or 6 mm²."
Provide the current basis, one-way route length, operating voltage, ambient and installation conditions, grouping, allowed voltage drop, connector or terminal model, destination market and documentation requirements. SINELINK can prepare a product and quotation response against those inputs.
Technical basis: IEC 60228 conductor-size and resistance context; IEC 62930 photovoltaic-cable scope; IEC 62548-1 PV-array design scope; current SINELINK product data. Final design must follow the applicable purchased standards, local rules, manufacturer instructions and approved project calculation.
