SINELINK / EV CHARGING BUYER GUIDE /
A procurement-focused guide to public charging payment, smart charging, Plug and Charge readiness and protocol planning
User-provided real-world scene. Used as an application illustration, not as a SINELINK customer-project claim.
Quick answer: AFIR is regulation; ISO 15118 is a communication standard
Do not treat AFIR and ISO 15118 as the same requirement. AFIR sets legal obligations for publicly accessible alternative-fuels infrastructure in the EU, including payment, price transparency, digital connectivity, data and smart-charging capability. ISO 15118 defines EV-to-EVSE communication functions such as Plug and Charge and, in ISO 15118-20, newer communication capabilities including bidirectional-power-transfer messages.
A buyer should therefore ask two separate questions: what must this public charging project legally provide in the destination market, and what ISO 15118 functions does the exact charger, vehicle ecosystem and backend actually support?
For wider system context, start with the commercial charging buyer guide. For protocol basics before reading this page, use the EV charging protocols overview.
1. The dates buyers should know
The dates below are a procurement checkpoint, not a substitute for checking the exact site, market, deployment date and applicable local implementation. The contract should identify the required scope instead of relying on a generic compliance claim.
13 Apr 2024
AFIR became applicable. New publicly accessible points deployed from this date fall under key payment and price rules.
14 Oct 2024
Publicly accessible recharging points need digital connection; relevant newer or renovated points must be capable of smart recharging.
Jul 2026
ISO 15118-20 Amendment 1 was published. Ask which edition and functions are actually implemented and tested.
1 Jan 2027
Relevant older public 50 kW+ points on TEN-T or safe parking areas need card/contactless payment planning. It is not a universal deadline for private chargers.
2. AFIR payment requirements change the hardware scope
A public charger quotation that only includes the power cabinet may not define a compliant public-site scope. Payment capability can change the terminal, screen, communication, backend and enclosure configuration.
- Publicly accessible charging must allow ad hoc charging rather than forcing every user into a long-term contract.
- For newly deployed public points from 13 April 2024, AFIR requires widely used electronic payment options; implementation depends on charger power and deployment context.
- At public points of 50 kW or more, ad hoc pricing is based on price per kWh; an occupancy fee per minute can additionally be used under AFIR.
- A QR or internet-based secure transaction can be relevant below 50 kW, while higher-power public charging has stricter card/contactless expectations.
- The payment requirement belongs in the project specification before the supplier fixes the display, terminal and software scope.
PAYMENT SCOPE
Payment is a site specification, not an accessory added after the order.
Freeze the expected payment method, display and backend workflow before the equipment configuration is finalized. The exact AFIR application still depends on the project facts and destination market.
3. Smart charging, OCPP and ISO 15118 solve different layers
These terms are often placed in one sentence, but they answer different technical and procurement questions. A project can use one without proving the others.
Site power management
Keeps total charging demand within a site or grid limit. Verify metering point, control logic, response time and fail-safe behavior.
OCPP / CSMS
Connects chargers to a central management system for sessions, status, remote control and optional smart charging. Verify exact OCPP version and profiles.
ISO 15118
Defines high-level vehicle-to-charger communication, including Plug and Charge functions. Verify exact part, version, certificate management and vehicle compatibility.
AFIR
Sets legal requirements for public infrastructure. Verify destination, public/private status, power, deployment date and payment/data obligations.
For site-level power control, see dynamic load balancing for commercial EV charging. For a detailed protocol comparison, reserve the OCPP 1.6J versus OCPP 2.0.1 comparison for the point where the required URL is available.
4. Plug and Charge is an ecosystem capability, not a single checkbox
A charger can list ISO 15118 support and still fail to deliver a usable Plug and Charge service if the complete certificate chain, backend, contract-certificate handling, vehicle support or PKI integration is missing.
- Ask which ISO 15118 part and implementation version the ordered firmware supports.
- Ask whether Plug and Charge has been tested with the intended CSMS and vehicle ecosystem, not only on a bench.
- Verify how contract certificates are installed, updated, revoked and monitored.
- Confirm fallback behavior when Plug and Charge authentication fails.
- Do not assume that ISO 15118 support means bidirectional charging is approved or available.
END-TO-END TESTING
A protocol label is not proof of an operating customer journey.
Contract language should freeze the firmware baseline, intended CSMS, certificate-management responsibility, test method and fallback behavior for the ordered configuration.
5. ISO 15118-20 matters because the standard is still evolving
ISO 15118-20:2022 is published and has a 2026 Amendment 1. At the same time, ISO 15118-2:2014 remains current while a second edition is still under development. Procurement language should name the exact standard edition and function set rather than saying only "ISO 15118 compliant".
Illustrative timeline. Confirm the applicable regulation, implementation date, and exact standards scope with the destination-market legal and technical team.
6. A 2026 EU public-charging RFQ should ask these questions
- Is the site publicly accessible under the applicable national implementation and AFIR context?
- What is each charging point's rated power and deployment date?
- What ad hoc payment hardware is included in the quoted configuration?
- How is price per kWh and any occupancy fee displayed before charging?
- Is the charger digitally connected and capable of smart recharging?
- Which OCPP version and certification profiles are supported by the ordered firmware?
- Which ISO 15118 functions are supported, and which are actually tested end-to-end?
- What certificate-management / PKI responsibilities sit with the charger supplier, CSMS and CPO?
- What data/API scope is provided for operational status, availability, and price?
- What country-specific electrical, metering and accessibility rules still need local review?
RFQ DISCIPLINE
Quote the exact public-site scope, not an abstract charger feature list.
The model, payment option, display, communications, firmware, and protocol functions should be identified together. A compliance statement without the configuration is too broad for a purchase order.
7. What SINELINK buyers should separate before ordering
Use the EV charging product hub to shortlist hardware and the project-solution overview for application context. Then request a compliance and protocol matrix for the exact model, destination and software configuration before placing the PO.
Separate conformity and certification-document checks from AFIR project obligations. Separate uptime and service obligations from a charger's technical feature list. The equipment, software and contract scope must be reviewed together.
MODEL-SPECIFIC REVIEW
The public-site scope must be frozen before the purchase order.
Share the destination market, public/private operating model, rated power, deployment schedule, payment requirement, backend, protocol functions and acceptance-test expectations for a model-specific review.
Frequently Asked Questions
Does AFIR require ISO 15118 on every EV charger?
No. AFIR and ISO 15118 are different. AFIR creates regulatory obligations for public infrastructure, while ISO 15118 specifies EV-to-EVSE communication. Check the exact AFIR requirement and the project interoperability needs separately.
Does AFIR require card payment at every public charger?
The payment method depends on charger power, deployment date and location. Higher-power public charging has stricter card/contactless requirements; buyers should verify Article 5 against the exact project.
Is Plug and Charge the same as OCPP?
No. Plug and Charge is primarily an EV-to-EVSE and certificate-ecosystem function associated with ISO 15118. OCPP connects charging stations to central management systems.
Does ISO 15118-20 automatically mean bidirectional charging is ready?
No. The standard defines relevant communication messages, but actual bidirectional operation also needs compatible hardware, vehicle support, grid rules, controls and approvals.
Is ISO 15118-2:2014 obsolete?
No. ISO states that the 2014 edition remains current, although a second edition is under development.
What changed in ISO 15118-20 in 2026?
Amendment 1 was published in July 2026 and adds content for AC DER service, MCS service and an improved security concept.
Should an importer accept "ISO 15118 supported" on a datasheet?
Not by itself. Ask which part, edition, functions, firmware and end-to-end tests are included.
What should be frozen in the purchase contract?
Freeze the exact model, hardware options, payment scope, protocol versions, certified profiles, ISO 15118 functions, firmware baseline, test evidence and responsibility matrix.
EU PUBLIC-CHARGING REVIEW
Freeze the model-specific compliance and protocol scope before the PO.